Living operational document tracking the path from v1.0.8 to public
launch as a SoundCloud-alternative. Compresses the original 24-week
plan to 6 weeks by explicit scope-control:

  - §2 Scope contract: IN/OUT/COMPRESSED matrix (what ships, what
    defers post-launch v1.1+, what's MVP-but-shippable)
  - §1 External actions EX-1 to EX-12 (legal, pentest, DMCA agent,
    DNS, TLS, CDN, OAuth secrets, Stripe live, transactional email,
    status page, coturn) with cycle estimates
  - §4 Day-by-day sprint breakdown for 6 weeks (W1 v1.0.9 + Ansible,
    W2 Postgres HA + obs, W3 storage HA + signature features,
    W4 PWA + HLS + faceted search + load test, W5 pentest + game day
    + canary + status page, W6 GO/NO-GO + soft launch + go-live)
  - §6 Risk register (R-1 to R-10) with mitigations
  - §7 Defended scope (refused additions during the 6 weeks)
  - §8 37 absolute Production-Ready criteria

Daily updates expected: tick acceptance criteria as they land, commit
each update with `docs: roadmap launch — <jour X> done`.