Veza Project Blueprint & Stabilization Plan
Current Status (2025-01-27)
Slogan: "Une fondation prometteuse minée par l'instabilité."
Component Status
- Backend (Go): ✅ Stable (92% test coverage).
- Chat Server (Rust): ⚠️ Fragile (Race conditions, poor error handling).
- Stream Server (Rust): 🚧 Skeleton / Work in Progress.
- Frontend (React): ❌ Broken / Blocking (TypeScript errors).
- Infrastructure: 🌀 Chaotic (Too many scripts, no central entry point).
- Common Code: 💔 Duplicated (
veza-commonvsveza-rust-common).
Stabilization Strategy
Principle: Stabilization before Evolution.
Phase 0: Preparation and Standardization (1-2 days)
- Goal: Simplify usages and remove technical debt.
- Unify Rust common crates (
veza-rust-commonintoveza-common). - Centralize commands via
Makefile(install, start, test, lint).
Phase 1: Make Project Usable (Frontend Focus - 3-5 days)
- Goal: Working web app connected to Go API.
- Fix TypeScript compilation errors.
- Pass basic UI unit tests.
- Connect Login/Register to Go API.
Phase 2: Core Services Reliability (Rust Focus - 1-2 weeks)
- Goal: Robust Rust services.
- Fix Chat server race conditions & error handling.
- Complete Stream server implementation & tests.
Phase 3: Controlled Evolution
- Goal: New features on stable base.
- New Go API routes.
- Expose Rust features via Gateway.
- Frontend integration of new features.